The Project

The Metz Solar Project (MSP or the Project) is a 115MWac, 141MWdc greenfield project located 15km east of Armidale (approximately 130km north-east of Tamworth) in NSW. The site is 430ha spread across land historically used for agricultural production. The site comprises a substation, solar panel array, and internal access tracks.

The Key Project components include:

  • photovoltaic solar modules (approximately 284,000 modules)
  • single-axis tracking module framing system mounted on steel piles
  • containerized Power Conversion Units (PCUs)
  • a substation containing transformers, associated switchgear and control and protection equipment
  • operations and maintenance buildings with associated car parking
  • road upgrade works on the site access route
  • above ground and underground cabling
  • internal all-weather access tracks
  • security system and security fencing
  • native vegetation plantings to provide visual screening
  • meteorological station(s); and
  • construction of a HV Connection to connect the Solar Farm Substation to the existing Transgrid substation located near the south western boundary of the Site.

PROJECT HIGHLIGHTS

Sydney Metro City & Southwest

Sydney Metro is a new stand alone railway network that will revolutionise the way Sydney travels.

Development of Bango Wind Farm

CWP Renewables is developing the Bango Wind Farm project in NSW.  Project Approval for the Bango Wind Farm was granted in December 2018 for the construction and operation of 46 wind turbines and associated infrastructure including a substation and transformers, underground and overhead cabling, operations and maintenance facility and access tracks.  The EPC Contract has been awarded to General Electric International Inc. (GE).

Australia JP9711-1 Core Simulation Capability (CSimC) Australia

In March 2019, the Australian Chief Information Officer Group (CIOG) awarded the JP9711-1 Core Simulation Capability to the Lockheed Martin Team. 

METZ Solar Farm

The Metz Solar Project involves the construction, operation and commissioning of a 115 megawatt (MWac) solar farm and associated infrastructure in the area of Metz, 15km east of Armidale, NSW.

gateway arrow image
gateway arrow image

GATEWAY